Updates on critical infrastructure installments
Notable developments are underway on the Main Electrical Building, which will house the plant’s high-voltage switchgear and motor drives, along with a dedicated generator room for the relocated 3MW generator from the IWRF.
Crews putting final touches on masonry walls
This week, the pace hasn’t slowed. Aerial shots reveal the evolving landscape around the Main Electrical and Blower Buildings, where crews are putting the final touches on masonry walls—setting the stage for the upcoming roof and slab work.
O&M building being prepped for concrete roof pour
This week, crews are tackling multiple tasks at once. The O&M building is being prepped for its concrete roof pour, while masonry walls are being waterproofed in anticipation of the colored veneer block installation.
Roof decking panels, masonry work, chlorine contact chamber all progressing
This week, the second floor of the Operations & Maintenance building is seeing major developments. On the maintenance side, roof bar joists are being placed, providing the framework for the next phase of construction.
Crews frame footers and slab in preparation for foundation concrete pours
This week, major developments are underway at the headworks as crews frame the footers and slab, preparing for foundation concrete pours next week.
Chlorine contact chamber reaching its final wall pour
This week, exciting developments are taking shape. At the Nereda basins, crews are making significant progress on the pipe support structure, a crucial step in delivering process air and electronic control to each reactor.
This week: major structural and mechanical advancements
The main electrical and blower buildings have reached an important phase with the completion of stem wall and column pours.
Main electrical building seeing substantial progress
This week, the main electrical building is seeing substantial progress with the footers being finalized to prepare for the installation of critical electrical infrastructure.
Chlorine contact chamber final wall pours complete by end of month
This week, the chlorine contact chamber construction is on track, with final wall pours scheduled by month-end. Inside the O&M building, substantial progress continues with interior framing and plumbing moving forward on the first floor.
Kicking off the new year with continued progress
Last week, on the final Wastewater Wednesday of 2024, we reflected on the significant progress of the FPUA sewer treatment plant on Energy Lane. Despite weather challenges and minor delays, construction is on schedule and within budget, with 50% of the work completed and most structures finished.
Wrapping up a productive 2024!
On the first day of 2025, a Wastewater Wednesday, we are full of gratitude and joy for the progress and updates that the last year has brought for the new FPUA sewer treatment plant being built on Energy Lane.
Masonry crews making strides on Operations and Maintenance building
This week, significant progress can be seen across several key areas of the project. Masonry crews are making strides on the Operations and Maintenance building, with work advancing rapidly on the maintenance bays.
Crews focused on first-floor interior framing
This week construction activities are advancing steadily. Crews are now focused on first-floor interior framing for the Operations and Maintenance building, while finalizing walls and slab work for the maintenance bays.
42-inch blind flange installed in the Nereda reactor wall
This week construction activities are advancing steadily. Crews are now focused on first-floor interior framing for the Operations and Maintenance building, while finalizing walls and slab work for the maintenance bays.
Aqua Nereda basins wrapping up concrete phase
This week marks significant progress across the site. The Aqua Nereda basins and sludge buffer tanks are wrapping up their concrete phase, with crews preparing to move forward with the installation of piping, equipment, and stairways.
New developments on exterior walls and second-floor decking
This week, progress continues with new developments on the exterior walls and second-floor decking of the Operations and Maintenance building.
Footers and slab framing nearing completion
The Operations and Maintenance building now features newly installed second-floor joists and decking, while the masonry walls of the maintenance bay continue to rise.
New flyover video of wastewater treatment plant
This week we are proud to share a flyover video of our new wastewater treatment plant being constructed on Energy Lane. This is a special look with a context that we couldn't provide in photos.
Significant progress on Nereda Basin site
This week, significant progress continues at the Nereda basin site. With the trough systems nearing completion, detailed views of the internal structure are now visible. The sludge buffer tank is also in its final stages, with walkways and plumbing nearing completion for optimized access.
Crews finishing wall on storage tanks
This week, we can see steady progress all throughout the up-and-coming Water Reclamation Facility being built on Energy Lane. The crews are finishing wall on the storage tanks, which are taking shape and nearing completion.
Thank you to the Florida Department of Environmental Protection for your generous support of $15 million granted toward this project. Disclaimer: This work is funded in part through a grant agreement from the Florida Department of Environmental Protection’s Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.