Guest Contributor Guest Contributor

Updates on critical infrastructure installments

Notable developments are underway on the Main Electrical Building, which will house the plant’s high-voltage switchgear and motor drives, along with a dedicated generator room for the relocated 3MW generator from the IWRF.

Read More
Guest Contributor Guest Contributor

Crews putting final touches on masonry walls

This week, the pace hasn’t slowed. Aerial shots reveal the evolving landscape around the Main Electrical and Blower Buildings, where crews are putting the final touches on masonry walls—setting the stage for the upcoming roof and slab work.

Read More
Guest Contributor Guest Contributor

O&M building being prepped for concrete roof pour

This week, crews are tackling multiple tasks at once. The O&M building is being prepped for its concrete roof pour, while masonry walls are being waterproofed in anticipation of the colored veneer block installation.

Read More
Rachel Tennant Rachel Tennant

Chlorine contact chamber reaching its final wall pour

 This week, exciting developments are taking shape. At the Nereda basins, crews are making significant progress on the pipe support structure, a crucial step in delivering process air and electronic control to each reactor.

Read More
Guest Contributor Guest Contributor

Kicking off the new year with continued progress

Last week, on the final Wastewater Wednesday of 2024, we reflected on the significant progress of the FPUA sewer treatment plant on Energy Lane. Despite weather challenges and minor delays, construction is on schedule and within budget, with 50% of the work completed and most structures finished.

Read More
Guest Contributor Guest Contributor

Wrapping up a productive 2024!

On the first day of 2025, a Wastewater Wednesday, we are full of gratitude and joy for the progress and updates that the last year has brought for the new FPUA sewer treatment plant being built on Energy Lane.

Read More
Guest Contributor Guest Contributor

Crews focused on first-floor interior framing

This week construction activities are advancing steadily. Crews are now focused on first-floor interior framing for the Operations and Maintenance building, while finalizing walls and slab work for the maintenance bays.

Read More
Guest Contributor Guest Contributor

Aqua Nereda basins wrapping up concrete phase

This week marks significant progress across the site. The Aqua Nereda basins and sludge buffer tanks are wrapping up their concrete phase, with crews preparing to move forward with the installation of piping, equipment, and stairways.

Read More
Guest Contributor Guest Contributor

Footers and slab framing nearing completion

The Operations and Maintenance building now features newly installed second-floor joists and decking, while the masonry walls of the maintenance bay continue to rise.

Read More
Guest Contributor Guest Contributor

New flyover video of wastewater treatment plant

This week we are proud to share a flyover video of our new wastewater treatment plant being constructed on Energy Lane. This is a special look with a context that we couldn't provide in photos.

Read More
Guest Contributor Guest Contributor

Significant progress on Nereda Basin site

This week, significant progress continues at the Nereda basin site. With the trough systems nearing completion, detailed views of the internal structure are now visible. The sludge buffer tank is also in its final stages, with walkways and plumbing nearing completion for optimized access.

Read More
Guest Contributor Guest Contributor

Crews finishing wall on storage tanks

This week, we can see steady progress all throughout the up-and-coming Water Reclamation Facility being built on Energy Lane. The crews are finishing wall on the storage tanks, which are taking shape and nearing completion.

Read More

Thank you to the Florida Department of Environmental Protection for your generous support of $15 million granted toward this project. Disclaimer: This work is funded in part through a grant agreement from the Florida Department of Environmental Protection’s Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.