Crews have begun setting up the tank wall forms
Today’s Wastewater Wednesday update shows some exciting new progress and the sustained forward momentum on the AquaNereda treatment basins and the reclaim storage tank.
The final Nereda tank foundation concrete pour is happening this week and the crews have already begun setting up the tank wall forms and reinforcement steel framing in preparation for the first wall pours later this month! We can also see the above ground reclaim storage tank’s ceiling dome start to really take shape as crews have been busy placing the plywood forms and steel in preparation for the concrete pour next week.
And finally, we see an interior shot of the reclaim tank that really illustrates the sheer amount of scaffolding and support framework that goes into building pre-stressed concrete tanks.